AMRT

Description

Provide labour, equipment, tools and material for the construction of track as per customer drawings and required industrial specifications.

Negotiate source, procurement & manage logistics of all Track Material including rail, ties, ballast, turnouts, tie plates, joint bars, anchors, compromise rails, lag screws, track spikes, and other OTM to meet CN Standards & Specifications for Industrial Track.

Work completed to meet or exceed CN Engineering Standards & Specifications for a HASMAT facility and Customer Satisfaction.

CN mainline turnouts constructed and installed within the track block time allotted with no disruption to  service.

 

Project consisted of the following:

Suppy & Construct New & Relay 115lb RE Track: 66,000 TF

Supply, Construct & Install Switches: 10 each #8-115 SGM, 13 each #10-115 SGM, 2 each #12-115 RBM CN mainline switches

Supply, Construct & Install DSP Derails : 2 each

Supply & Install Bumper Posts: 19 each

Supply & Construct Plank Crossing: 25 each

Supply & Install Ballast: 46,500 Tonnes

Lift,Line & Surface: all track & switches

Trackage inspected by qualified Cariboo Supervisor with Northern Plains Engineer and CN Engineering approving the structure for operating  service.

Project
Alberta Midland Rail Terminal

Location
Lamont, AB

Client
Northern Plains Rail Services