Description
Provide supervision, labour, equipment, and tools for the construction of track and re-alignment/refurbishment of existing track as per engineering design drawings to CN Engineering Standards and Specifications. Construction was 50% wood tie and 50% concrete tie. All track material was supplied by CN. Work was performed under traffic within work blocks determined with CN Transportation.
Project consisted of the following:
Construction of New 136lb Track: 25,300 TF
Realignment/Refurbishment of Existing Track: 13,120 TF
Construct & Install Switches: 7 each #12-136 RBM mainline
Unload & Place Ballast: 340 cars
Lift, Line & Surface: 38,420 TF
Destressing: 38,420 TF
Thermite Welding: 233 Welds
Trackage inspected to inspected Sept 30/18 and approved for operating service.