Description
Provide labour, equipment, tools and material for the construction of track as per customer drawings and required industrial specifications.
Negotiate source, procurement & manage logistics of all Track Material including rail, ties, ballast, turnouts, tie plates, joint bars, anchors, compromise rails, lag screws, track spikes, and other OTM to meet CN Standards & Specifications for Industrial Track.
Work completed to meet or exceed CN Engineering Standards & Specifications for a HASMAT facility and Customer Satisfaction.
CN mainline turnouts constructed and installed within the track block time allotted with no disruption to service.
Project consisted of the following:
Suppy & Construct New 100lb RA Track: 17,852 TF
Supply, Construct & Install Switches: 6 each #8-100 SGM, 2 each #10-115 RBM CN mainline
Supply, Construct & Install DSP Derails: 2 each
Supply & Install Bumper Posts: 7 each
Supply & Construct Plank Crossing: 4 each
Supply & Install Ballast: 12,000 Cu.Yards
Lift, Line & Surface: all track & switches
Bonding & Grounding: Loading & Scale track
Trackage inspected by qualified Cariboo Supervisor, Devco Engineer and CN Engineering approving the structure for operating service.